Required Inspections

This is not intended to be a complete list of all required inspections.

  • All footings are inspected after excavation and before pouring concrete.
  • All slabs are inspected prior to pouring concrete with all steel in place.
  • Concrete walls are inspected prior to pouring concrete with all steel in place.
  • Backfill / foundation drainage inspection prior to burying habitable basements.
  • All plumbing & gas piping and electrical conduit or wiring prior to covering ditch.
  • All gas lines, fuel lines, water & sewer lines must be pressure tested.
  • Rough-in inspections of plumbing, electrical, hvac & gas prior to concealment.
  • Framing inspection of floors, walls and roofs prior to insulating.
  • Insulation inspection prior to hanging drywall.
  • Fireplace hearth inspection prior to pouring concrete with all steel in place.
  • Inspection required on all electrical services prior to connection by power company.
  • Final inspection.
  • Electrical bonding & steel placement inspection for all pools.

 

Special inspections as required